Vikramshila Setu Update: ‘Bailey Bridge’ will be ready in May, vehicles up to 10 tonnes will be able to pass through it
Sandy Verma | May 9, 2026 9:24 PM CST

Independent morning M Roshan Bihar Bureau

Publisher – Jitendra Kumar Rajesh

Bihar There is relief news for the people facing traffic problems on Vikramshila Bridge. The NH Department, Bridge Construction Corporation and Border Roads Organization (BRO) have geared up to repair the damaged part of Vikramshila Bridge and restore traffic. The final decision to build a temporary ‘bailey bridge’ on the damaged portion was taken at a high-level joint meeting held on Thursday.

Bailey Bridge: Budget of Rs 3 crore and length of 50 meters. The administration plans to complete this bridge within the month of May. This bridge will be capable of carrying a load of up to 10 tonnes. ​Who will be able to walk on this Bailey Bridge? Ambulances, bikes and small four-wheelers will be able to walk on it easily. But there will be a complete ban on the entry of heavy trucks and overloaded vehicles.

how much will it cost
The construction of this temporary structure is estimated to cost approximately Rs 3 crore. ​Along with the Bailey bridge, a two-lane truss bridge will also be built parallel to the bridge. There will be a separate safe passage for pedestrians, so that local people do not face any danger while walking. What was the reason for the accident? Shocking flaws revealed in the investigation. The team led by Manoj Kumar, Senior Divisional Engineer (Bridge) of Danapur Railway Division, conducted a technical investigation of the bridge.

The report highlights serious construction mistakes:

Design changes: The original 24 meter slab had to be increased to 34 meters due to pillar subsidence, which increased the pressure on the structure. Effect of the jam: The long jam on the bridge that continued for 24-48 hours badly damaged the ‘expansion joint’ and ‘bearing’. Heavy pressure: The pressure of modern heavy vehicles on this bridge, which was built in ancient times to accommodate 6-wheel trucks, weakened the slab.

When will the work start?

NH Chief Engineer Sanjay Bharti said that the detailed report of the experts has been sent to the Ministry of Road Transport and Highways (MoRTH). ​A formal letter regarding restoration will be sent to the ministry on Saturday. ​June 15: The target is to start the work of permanent repairing of the damaged part. The entire project will be supervised by Bihar State Bridge Construction Corporation. Construction of Bailey Bridge will prove to be a ‘lifeline’ to connect the broken connectivity between Bhagalpur and Navgachia. As soon as the green signal from the ministry is received, work will be started on war footing. Stay connected to our portal for such latest news.